Work on Jordan Gate Towers begins in August

sixth circle
Cranes stand outside the Jordan Gate Towers in Amman. (File photo: Jordan News)
AMMAN — Renovation of the Jordan Gate Towers will resume in August and work will be carried out in three phases, Greater Amman Municipality (GAM) spokesperson Nasser Al-Rahamneh said.اضافة اعلان

The project started in 2005 and was supposed to be completed five years later. But work suddenly stopped in 2006 and the high-class commercial and residential structures are still seen standing tall and dominant in West Um Uthaina near Sixth Circle.

Rahamneh said GAM is taking part in the project and that the first stage of work will start in August and end in next May.

“The first phase comprises of preparing the implementation plans, which include architecture and construction, drawing up the contractors’ contracts and a list of specifications,” he said.

He noted that the initial renovation will also include finishing up work on the exterior of the structures, and isolating the towers to protect them from weather conditions.

The second phase, he added, will focus on the northern tower, which boasts of luxurious apartments and a shopping mall. He said work on the tower, which is linked to its southern twin through a multi-story podium, will begin May 2023 and be completed by December 2024.

The third stage, which includes the southern tower, will begin in March 2023.

Rahamneh said he did not have details on the cost, saying the figures will be announced after the “tenders are approved”.

GAM agreed to become a partner in the project since it is a “national institution, which works to stimulate the wheel of the economy, to enhance the infrastructure across the Kingdom.”

He pointed out that GAM’s work “reflects on people’s lives in the various fields”. He said that was GAM’s goal being a partner in the Jordan Gate Towers project.